Why Doesn’t Cheap Power Make Electricity Cheap?

Solar panels and turbines can be manufactured by the million. A transmission corridor is negotiated one landscape at a time. As generation gets cheaper, the scarce product is increasingly permission and time to move power.

Last updated September 2026
Figure 1 · Four ways to create transfer capacity

The corridor is often the scarce asset

Advanced reconductoring

A low-sag, high-temperature conductor can put substantially more aluminium on an existing route without rebuilding every tower. It turns the hardest-won part of a line, the corridor, into reusable infrastructure.

Capacity effect
Up to roughly 2×
Deployment
About 1–3 years where feasible
Land requirement
Keeps towers and right-of-way

Limit: Tower strength, clearances, substations, outages, and downstream equipment can cap the usable uplift.

Ranges describe categories, not project quotations. Actual capacity, cost, and schedule depend on voltage, topology, equipment limits, outages, terrain, and the approvals a project requires.

What the record shows

  • At the end of 2025, 2,061 GW (1,312 GW of generation and 749 GW of storage) was actively seeking U.S. transmission interconnection, down 10% year over year and 21% from the 2023 peak of 2,598 GW (Measured).
  • Only 13% of capacity requesting interconnection from 2000 through 2020 had reached commercial operation by the end of 2025; 75% had withdrawn (Measured).
  • The median time from request to operation was about 22 months for projects built in 2008, 36 months for 2015, and 61 months for projects completed in 2025 (Measured).
  • A review cited by the U.S. Department of Energy found new transmission projects take about ten years on average. Existing corridors can sometimes be upgraded in one to three.

Queue capacity is measured developer interest, not expected completion. Technology uplift is conditional, not additive. Timelines describe observed or reported classes of projects, not a promise for any individual line. Evidence labels used here: Measured (directly demonstrated), Derived (calculated from measured data), Projected (modeled future outcome), Target (announced goal), and Editorial inference (interpretation of evidence).

Part I: The new scarcity

Electricity can be cheap and still be stranded

A generator produces at a node, not everywhere. Its economic output is the energy that can cross the network after losses, operating limits, contingencies, and congestion, not the energy it could produce in isolation.

That distinction becomes decisive when wind and solar equipment gets cheaper and faster to deploy than the network around it. A low bid at a windy site is not a delivered price to a city. The missing terms include interconnection upgrades, substations, long-distance transfer, congestion, curtailment, reserves, and the years during which capital waits for access.

Generation+Network + congestion+Time and curtailment

The unit that matters is commissioned transfer

~10 yearsAverage end-to-end duration in a DOE-cited review of more than 30 new transmission projects.
1–3 yearsReported deployment window for many grid-enhancing technologies and feasible reconductoring projects.
20–64%Median additional within-region deployment need by 2035 in DOE's moderate- and high-clean-energy scenario groups.

Cost per mile hides voltage and power. Cost per megawatt-mile is better, but still ignores utilization and schedule. The most revealing ledger records dollars, firm transfer capability, congestion relieved, and years to energization together.

Part II: The queue

A waiting list became a market signal

Interconnection studies determine the network upgrades required to connect a proposed plant and who initially pays for them. As requests multiplied, a serial engineering process became a portfolio-selection problem.

2,061 GWActively seeking interconnection at the end of 2025: 1,312 GW of generation plus 749 GW of storage (Measured).
549 GWQueued capacity with a draft or executed interconnection agreement but not yet operating (Measured).
13%Share of 2000–2020 requested capacity that had reached operation by the end of 2025; 75% withdrawn (Measured).

Time is the price this market charges. Among projects that reached operation, the median request-to-operation span ran about 22 months for the 2008 cohort, 36 months for 2015, and 61 months for projects completed in 2025 (Measured, Berkeley Lab), nearly a tripling across three cohorts. The stages split similarly: about 45 months from request to interconnection agreement, then a median 31 months from agreement to operation in 2025, against 21 months in 2008 (Measured).

Throughput explains why the queue is shrinking while the clock stays long. Active capacity stood at 2,061 GW at the end of 2025 (1,312 GW generation, 749 GW storage), down 10% year over year and 21% from the 2023 peak of 2,598 GW, as more than 750 GW withdrew during 2025 alone (Measured). The active mix is solar 773 GW, storage 749 GW, gas 253 GW (up 86%), and wind 220 GW (Measured). With 549 GW holding an interconnection agreement but not yet operating, a falling queue mostly records attrition, not faster delivery.

The queue is therefore neither a forecast nor pure noise. It records the option value developers place on network access. Withdrawal can mean a speculative proposal failed; it can also mean upgrade costs, study delays, land, procurement, financing, or power contracts made an otherwise buildable plant uneconomic.

The bottleneck has two clocks

ClockEarlier benchmarkRecent benchmarkWhat it measures
Generator interconnection22 months · projects built 200861 months · projects built 2025Request to commercial operation among projects that finished.
Federal environmental reviewFragmented agency processes~4-year historical average; two-year CITAP targetNotice of intent to record of decision, not the whole project.
New transmissionProject-specific~10 years average in DOE-cited reviewDevelopment through completion across 30-plus projects.
Existing-corridor upgradeStatic operationOften 1–3 years where feasibleGETs or reconductoring without a new right-of-way.
Part III: The cost stack

The wire is only one layer of a transmission line

Steel, aluminium, copper, insulation, concrete, and power electronics are tangible. The route, approvals, system studies, beneficiary agreement, construction windows, and operating rules determine whether those materials become useful infrastructure.

01

Choose a need

Forecast load, retirements, generation, reliability events, and trade across a network whose future is uncertain.

Layer
Planning
Output
Commissioned, operable transfer capability
02

Decide who benefits

A line can lower energy cost, improve reliability, and unlock generation in different places. Agreement over who pays often precedes engineering.

Layer
Cost allocation
Output
Commissioned, operable transfer capability
03

Secure a path

Rights-of-way, state and federal approvals, environmental review, tribal consultation, landowner agreements, and community design define the buildable route.

Layer
Siting
Output
Commissioned, operable transfer capability
04

Build the terminals

Substations, breakers, transformers, converter stations, protection, and controls determine whether conductor capacity can enter the operating grid.

Layer
Equipment
Output
Commissioned, operable transfer capability
05

String and commission

Towers, foundations, conductors, access roads, specialist labour, outages, testing, and market integration finally create usable transfer capability.

Layer
Construction
Output
Commissioned, operable transfer capability

The physical floor is lower than the delivered project

Ohmic loss is unavoidable: current heats a conductor in proportion to current squared and resistance. Higher voltage moves the same power with less current, which is why long-distance systems climb from distribution voltages to hundreds of kilovolts and why HVDC becomes attractive for particular long, controlled transfers.

But today's dominant gap is rarely between conductor performance and a thermodynamic limit. It is between a viable electrical design and a commissioned asset. The materials set a floor; coordination sets much of the premium and the variance.

Part IV: The option in the ground

An existing corridor is a platform

Once a route has towers, access, easements, known neighbours, and a place in operating models, its reuse can avoid the slowest parts of a greenfield project.

Dynamic line ratings measure weather and conductor conditions instead of assuming a conservative fixed limit. Power-flow controls redirect electricity around overloaded elements. Topology optimization finds better network configurations. Advanced conductors can tolerate higher temperatures with less sag and, on suitable structures, roughly double capacity.

These are not four versions of free capacity. A windy-day rating is variable. A rerouted flow consumes headroom elsewhere. A stronger conductor may expose a substation limit. Reconductoring requires outages and structures that can accept the design. Their value is speed: they buy time and transfer while the system decides where genuinely new corridors are unavoidable.

Upgrade before expansion, but do not confuse them

Operate

Measure and route

Reveal thermal headroom and use the network's spare paths more deliberately.

Fastest · variable or topology-dependent gain
Rebuild

Reconduct and uprate

Reuse a permitted route while replacing wires and, where needed, terminal equipment.

Medium term · potentially near-2× line capacity
Expand

Add new corridors

Create firm geographic transfer that optimization and existing rights-of-way cannot supply.

Slowest · largest structural network change
Part V: Institutions are equipment

A regional plan is part of the machine

Transmission creates multiple products over decades: energy savings, reliability, resource adequacy, resilience, reduced losses, access to generation, and insurance against futures that never arrive exactly as forecast.

Planning only for the first generator that requests service tends to produce piecemeal upgrades and repeated studies. Planning for a portfolio can identify shared facilities, but immediately raises the political question: which future benefits count, and which customers should fund them?

FERC Order No. 1920 requires long-term regional transmission planning and consideration of a broader set of benefits. Order No. 2023 moved generator interconnection toward first-ready, first-served cluster studies. Rules can shorten duplicated work, but they cannot manufacture transformers, settle every state dispute, or create local consent. Reform succeeds when measured in energized capacity and lower congestion, not filings completed.

Planning is sequential

The business case, regional plan, beneficiary analysis, route, permits, equipment orders, and construction cannot all begin at once. Delay at one layer idles the rest.

The cheapest line can be unbuildable

A direct path may cross too many jurisdictions or sensitive landscapes. Route changes raise length and cost before material is purchased.

A line is a network intervention

Its value depends on generation, load, neighbouring constraints, dispatch, and contingencies. Dollars per mile alone cannot describe the useful output.

Transformers can become the clock

A conductor upgrade that outruns terminal equipment simply moves congestion into substations, breakers, and protection systems.

Queues contain options, not forecasts

Developers submit projects under uncertainty and most historical queued capacity has not reached operation. Queue volume measures demand for access, not future supply.

Local costs and broad benefits diverge

Communities host towers and land impacts while reliability and market savings spread across regions. Durable consent needs a distributional answer, not only a net-benefit model.

Who is building what

Advanced carbon-core conductors, dynamic line rating, modular power flow hardware, and multi-gigawatt HVDC links address transmission constraints. Search the record, or filter by grid layer.

9 programmes
CTC GlobalACCC ConductorAluminum Conductor Composite Core replacing steel cores with carbon-glass composites, doubling current capacity with negligible thermal sag
Reported evidence
Over 160,000 km installed in 60+ countries; reconductoring existing rights-of-way achieved 2× capacity gains without new towers.
Announced next step
Universal standard for utility transmission line upgrades across high-congestion corridors.
Unresolved risk
Higher upfront material cost per foot, specialized installation training to avoid core snapping, and hardware fitting compatibility.
TS ConductorCarbon-Composite Transmission CableHigh-efficiency aluminum conductor with encapsulated carbon fiber core designed to cut line losses by up to 50% under standard loads
Reported evidence
Pilots and utility deployments with MidAmerican Energy, Montana-Dakota Utilities, and Tennessee Valley Authority (TVA).
Announced next step
Rapid reconductoring of constrained renewable interconnect lines across MISO and ERCOT.
Unresolved risk
Supply chain scaling for high-modulus carbon fiber and utility reluctance to deviate from 100-year-old ACSR standards.
LineVisionNon-contact Dynamic Line RatingLiDAR and optical sensors monitoring line sag, conductor temperature, and ambient wind to calculate real-time Dynamic Line Ratings (DLR)
Reported evidence
Installed on thousands of circuit miles across National Grid, AES, and Duquesne Light, unlocking 10–40% additional transmission capacity.
Announced next step
System-wide integration with utility energy management systems (EMS) for automated real-time dispatch.
Unresolved risk
Regulatory frameworks that compensate utilities on capital expenditure rather than throughput efficiency, slowing software adoption.
Smart WiresSmartValveModular, tower-mounted static synchronous series compensators that dynamically inject capacitive or inductive reactance to balance line flows
Reported evidence
Commercial deployments with National Grid ESO (UK), Transgrid (Australia), and Central Hudson, diverting power from overloaded lines to underutilized paths.
Announced next step
Modular grid modernization packs deployed in months rather than decade-long new line builds.
Unresolved risk
Interaction with complex substation protection relay schemes and high sub-cycle transient fault currents.
Prysmian Group525 kV Extruded HVDC CablesHigh-voltage direct current submarine and terrestrial underground cables with XLPE insulation rated up to 525 kV and 2+ GW capacity
Reported evidence
Contracted and supplying major European interconnections (German SuedLink, SuedOstLink) and US offshore wind transmission projects.
Announced next step
Manufacturing cables rated for 2.5 GW single-bipole circuits with reduced conductor electrical resistance.
Unresolved risk
Multi-year manufacturing lead times, specialized cable-laying vessel scarcity, and terrestrial trenching permitting hurdles.
Hitachi EnergyHVDC LightVoltage Source Converter (VSC) technology with modular multilevel converters (MMC) enabling black-start capability and independent active/reactive control
Reported evidence
Core converter stations operating on Champlain Hudson Power Express (New York) and Dogger Bank offshore wind links in the North Sea.
Announced next step
Standardized multi-terminal DC grids enabling mesh networking of offshore and inter-regional transmission.
Unresolved risk
DC circuit breaker development for large multi-terminal mesh networks and multi-billion-dollar substation capital budgets.
Siemens EnergyHVDC PLUSModular multilevel converter systems with compact converter footprint and dry-type capacitors for multi-gigawatt power transmission
Reported evidence
Selected for key corridors in the German Energiewende and interconnector projects connecting Ireland and the UK.
Announced next step
High-availability converters with sub-0.5% conversion losses per station.
Unresolved risk
Supply chain bottlenecks in power semiconductors (IGBTs/SiC) and long-lead transformer deliveries exceeding 3–4 years.
InvenergyGrain Belt ExpressApprox. 800-mile, 600 kV overhead HVDC merchant transmission line moving 5 GW of wind and solar from Kansas to Illinois and the PJM grid
Reported evidence
Secured major state regulatory approvals across Kansas, Missouri, and Illinois; obtained federal environmental permitting clearances.
Announced next step
Commercial commissioning to bridge the divide between low-cost SPP generation and high-cost PJM demand centers.
Unresolved risk
Eminent domain litigation, landowner opposition, and coordinating cost allocation across distinct regional transmission organizations.
FERC / Regional Transmission OrganizationsOrder 2023 & Order 1920Federal regulatory reforms mandating cluster study processes for interconnection queues and 20-year long-term transmission planning
Reported evidence
RTOs (MISO, PJM, SPP) implemented first-ready, first-served queue rules, penalizing speculative interconnection requests.
Announced next step
Clearing the 2,000+ GW queue backlog of waiting clean energy and battery storage projects.
Unresolved risk
Litigation over inter-regional cost allocation and state vetoes over federally mandated regional transmission corridors.

Conductor and DLR capacity gains refer to thermal transfer limits; actual operating throughput is frequently constrained by downstream contingency criteria (N-1) and system voltage stability.

An optimistic view, with conditions

The grid has a faster lane and a durable lane

Measure, control, and reconductor existing lines now; plan new regional corridors before each individual project proves the need again. The technologies are complementary because one buys years and the other buys geography.

Now

Expose headroom

Deploy ratings, controls, topology tools, storage, and queue reform where they can release capacity without new land.

Next build cycle

Reuse corridors

Reconduct suitable routes and upgrade the substations and protection systems that would otherwise become the next bottleneck.

Durable network

Plan across futures

Build high-capacity regional and interregional paths whose reliability and market value survive any single generator proposal.

Generation cost and the customer bill have different boundaries

IEA estimated about $400 billion of annual global grid investment in 2025 versus roughly $1 trillion in generation assets. Its 2026 grid assessment says planning, permitting and building network infrastructure can take 5–15 years, longer than typical new solar and wind projects. This is a timing mismatch as well as a capital-cost gap: a cheap generator in a queue cannot deliver cheap energy to load.

In the United States, Berkeley Lab counted 2,061 GW of generation and storage active in interconnection queues at the end of 2025, down from a nearly 2,600 GW peak in 2023. Most queued capacity will not be built, so the figure is a development backlog rather than future supply. At the retail boundary, EIA puts 2025 average US residential electricity at 17.30¢/kWh and industrial electricity at 8.62¢/kWh. Those categories buy different voltage, distribution and service arrangements and cannot be directly compared with a plant’s levelized generation cost.

EIA found US residential prices rose from a little over 12¢/kWh in 2013 to about 16¢ in 2023 in nominal terms, but less than 1% after inflation. That distinction prevents a false “cheap power, soaring real bills” inference from nominal prices alone. The stronger test is delivered cost in a fixed place and hour, including congestion, network upgrades, reliability capacity and customer-side charges.

A cheap plant is one line of a delivered bill

EIA’s 2025 retail data span 8.20¢/kWh in North Dakota to 35.72¢/kWh in Hawaii across all customer classes. EIA distinguishes generation and fuel from transmission, distribution, financing, reliability and fees; a solar auction price therefore cannot be subtracted directly from a household tariff. In its 2024 transmission assessment, DOE cited US within-region congestion costs of roughly $7 billion in earlier years, more than $13 billion in 2021 and $20 billion in 2022. Those are system estimates, not an allocation to each household.

Network delay adds a second multiplier. DOE’s same assessment shows the mean request-to-operation interval for new US plants rising from about two years in 2008 to about five years in 2023. The National Transmission Needs Study finds congestion value concentrated in a small share of hours, so annual average energy prices miss the local, time-specific cost of moving power. This is why published line losses alone cannot explain the delivered-price gap. A usable comparison needs the same location, hour, voltage level and reliability obligation; publicly available international tariffs rarely meet all four boundaries.

Sources, method, and boundaries

This report treats queue entries as applications, nameplate uplift as conditional engineering potential, and targets as targets. It does not collapse overhead lines, underground cables, HVAC, HVDC, interconnection upgrades, or bulk regional facilities into one misleading cost curve.